Elbert County’s development pipeline includes two large residential proposals, a utility-scale solar project and a planned agricultural and industrial park at different stages of review, according to the county’s Sept. 16 development report.
The Ridge at Spring Valley, also identified as Moorstead PUD, proposes 633 single-family homes near County Roads 21 and 174. CoyoteRidge proposes 221 residential lots, parks and open space on about 112 acres near County Roads 13 and 178. Both preliminary plats were listed as Formal Application, a stage indicating the applications were complete and in process; neither has been approved.
CoyoteRidge’s preliminary-plat case, PP-2026-0002, is scheduled for a Planning Commission hearing Dec. 1 at 6 p.m. and a Board of County Commissioners hearing Dec. 16 at 1 p.m., according to the county’s public hearing notice. The notice says the hearings may begin later than the listed times.
County referral comments flagged a title issue involving 0.31 acre split from the larger parcel in 2023. The Assessor said the piece is owned by someone other than Coyote Ridge LLC and that the discrepancy must be remedied. The third-referral comments also require a computer-aided-design file when the final plat is recorded and say the applicant must address prior comments from CORE Electric Cooperative before final-plat approval. CORE had no additional comments on the preliminary plat, but its earlier requirements remain due before that later approval.
County Public Works and Engineering require the developer to put its offsite road-improvement commitment on the plat. Interim work at County Roads 178 and 13 includes improvements to the north and east legs and eastbound and westbound left-turn lanes under all-way stop control. The developer must also dedicate right-of-way and contribute at least 25% toward eventual intersection improvements, either a specified signal design or a feasible single-lane roundabout. The county may seek proportionate contributions for other intersections affected by project traffic.
The preliminary drainage report and referral comments asked for support for some drainage calculations and flagged inconsistent imperviousness figures for one basin. County staff’s report says revisions addressed referral concerns and no agency objections remained. Detailed drainage design is still expected during later final-plat and construction-plan review.
The staff report lists a proposed $304,400 payment to Douglas County School District, equivalent to $64,850 per acre, as a possible condition before final-plat recordation. The amount is described as cash in lieu of land dedication; it is not established as a final condition or a payment already made.
The property is already zoned Planned Unit Development, approved in 2025 for up to 221 lots. The county report says the proposal includes 47.5 acres of open space and would use central water and sewer supported by a metropolitan district. Approval of the preliminary plat would not itself authorize construction; final-plat approval and additional permits are required. CoyoteRidge’s metropolitan-district service plan was approved in August and was listed as awaiting final recordation in the September development report.
The Ridge’s separate service plan for five metropolitan districts was approved by the Board of County Commissioners on Sept. 9, subject to two forms of notification and an agreement with Elizabeth Parks & Recreation. That approval covered the service plan, not the preliminary plat.
Buffalo Grass Solar is listed at the Community Meeting stage. The proposal includes 398 megawatts of solar generation and 200 megawatts of battery storage. A community meeting was held July 22, and the September report did not list an October or November hearing for the solar project or its related special-use application.
Colorado Plains Ranch was listed at the Hearing/Decision stage as a master-planned agricultural and industrial park. The September report had scheduled Planning Commission and Board of County Commissioners hearings for Nov. 4 and Nov. 18. The records used for this update do not establish the outcomes.