Kiowa County schedule sets tiered land-use permit charges
Power-plant applicants face higher fees, deposits and maintained balances than other projects; applicants also cover county review costs.
Reporting, public meetings, and local issues affecting Kiowa County.
Featured
Kiowa County
Power-plant applicants face higher fees, deposits and maintained balances than other projects; applicants also cover county review costs.
Kiowa County
The charge applies to applicants seeking county 1041 permits and is included in the county’s separate $11,788.39-per-megawatt renewable-energy schedule.
Kiowa County
The new schedule allocates charges for roads, emergency services, landfill and other public costs.
Kiowa County
SWCA estimates $1.316 million in mitigation for a 550-megawatt example project, compared with about $6.879 million in the county and THK study; Invenergy also objects to baseline costs, double-counting and existing mitigation obligations.